by LAR | Sep 30, 2020 | Capital Project Timeline
September 2020 Cafe Skimmed. Progress on new stage. Ground floor toilets...
by LAR | Aug 31, 2020 | Capital Project Timeline
August 2020 Cafe ceiling insulation put...
by LAR | Jul 31, 2020 | Capital Project Timeline
July 2020 Plasterboard to bar area. Loft space...
by LAR | Jun 30, 2020 | Capital Project Timeline
June 2020 Lead flashing repair to...
by LAR | May 29, 2020 | Capital Project Timeline
May 2020 Frame erected for auditorium acoustic...
by LAR | Mar 31, 2020 | Capital Project Timeline
March 2020 Cafe ceiling put in. First floor bar plastered. Trusses...